Client: Independent Preparatory School
Educational New Build
- Programme 37 weeks
- New two storey structure to house high quality classrooms
- Client required durable and high quality finishes to the toilet facilities, ceiling partitions, joinery and decorations
- Security and logistical concerns were overcome as the school was still in full occupation, consequently all deliveries were scheduled to avoid the school drop-off and pick-up periods
- Access to the site was limited and so the delivery of goods onto site was carefully planned and executed